Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam EX0-008 All Questions

View all questions & answers for the EX0-008 exam

Exam EX0-008 topic 1 question 27 discussion

Actual exam question from Exin's EX0-008
Question #: 27
Topic #: 1
[All EX0-008 Questions]

What is the usual length of the time box for the complete Sprint Planning meeting?

  • A. Four hours for a 30 day Sprint, one to two hours for a shorter Sprint.
  • B. However long it takes to complete the Sprint Backlog.
  • C. Never more than two hours, regardless of Sprint length.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Bojana
3 years, 4 months ago
"Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter."
upvoted 1 times
...
alexandrustefanescu
3 years, 4 months ago
Actually is an 8 hour for 30 Days ..
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...