Which information Radiator can the team use best during the Sprint to track the work?

  • A. Gantt chart
  • B. Product Backlog
  • C. Release Burn Up
  • D. Task board
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
juzer
Highly Voted 4 years, 7 months ago
Task board
upvoted 6 times
...
Rume
Most Recent 4 years, 3 months ago
Answer is D
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...