Question #: 9
Topic #: 1
[All ASM Questions]

You are a project manager for a midsize software company, which still uses the Waterfall model. Your customer wants a new software project.
When should you consider the use of Agile?

  • A. The product definition is stable and will not change.
  • B. The scope lacks specificity and is unlikely to remain stable.
  • C. The user technology to be developed is understood.
  • D. There are almost no ambiguous requirements.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
juzer
4 years, 10 months ago
The scope lacks specificity and is unlikely to remain stable.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago