Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam ASM All Questions

View all questions & answers for the ASM exam

Exam ASM topic 1 question 1 discussion

Actual exam question from Exin's ASM
Question #: 1
Topic #: 1
[All ASM Questions]

Your team uses Story Points to estimate User stories.
Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other
Stories.
How should you address this?

  • A. Complete incomplete Stories
  • B. Increase or re-estimate Velocity
  • C. Re-estimate all small Stories
  • D. Switch to using Ideal days
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
4e5c540
2 months, 1 week ago
"A" Is the answer
upvoted 1 times
...
juzer
4 years, 7 months ago
Complete incomplete Stories
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...