exam questions

Exam ASF All Questions

View all questions & answers for the ASF exam

Exam ASF topic 1 question 47 discussion

Actual exam question from Exin's ASF
Question #: 47
Topic #: 1
[All ASF Questions]

During a Sprint Planning session, the team argues about the work estimates for a particular story.
✑ The Product Owner estimates five days.
The Lead Architect estimates two days.

✑ The Scrum Master estimates eight days.
✑ The team member working on it estimates seven days.
What value (in days) should be used for planning?

  • A. 2
  • B. 5
  • C. 7
  • D. 8
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
pothepanda
3 weeks ago
Selected Answer: C
The correct answer is C (7 days). The estimate from the team member who will actually perform the work should be used, as they have the best understanding of the effort required and will be responsible for completing it. Other stakeholders like the Product Owner and Scrum Master should not be providing estimates as this isn't their role in Scrum.
upvoted 1 times
...
james2033
4 months ago
Selected Answer: B
(5 + 2 + 8 + 7)/4 = 22/4 = 5.5
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago