Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam ASF All Questions

View all questions & answers for the ASF exam

Exam ASF topic 1 question 47 discussion

Actual exam question from Exin's ASF
Question #: 47
Topic #: 1
[All ASF Questions]

During a Sprint Planning session, the team argues about the work estimates for a particular story.
✑ The Product Owner estimates five days.
The Lead Architect estimates two days.

✑ The Scrum Master estimates eight days.
✑ The team member working on it estimates seven days.
What value (in days) should be used for planning?

  • A. 2
  • B. 5
  • C. 7
  • D. 8
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
james2033
1 year, 1 month ago
Selected Answer: B
(5 + 2 + 8 + 7)/4 = 22/4 = 5.5
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...