During a Sprint Planning session, the team argues about the work estimates for a particular story.
✑ The Product Owner estimates five days.
The Lead Architect estimates two days.
✑ The Scrum Master estimates eight days.
✑ The team member working on it estimates seven days.
What value (in days) should be used for planning?
pothepanda
2 months agojames2033
5 months, 2 weeks ago