A Manager requests to attend the daily stand-up meeting so that he can be more responsive to the team by being aware of the team's progress and issues. As the Scrum Master, what should you do?
A.
Allow the Product Owner to participate in 'listen only' mode.
B.
Allow the Product Owner to participate like any other team member.
C.
Turn down the request as the daily stand-up is only for the team.
The daily stand-up meeting is a time-boxed event that is specifically designed for the Development Team to synchronize and plan their work for the upcoming day. It is not intended for stakeholders, such as managers or customers, to participate, as their presence could disrupt the focus and flow of the team. The Scrum Master should explain to the Manager that the daily stand-up is only for the Development Team and encourage the Manager to work closely with the Product Owner to get updates on the project's progress.
Correct Answer is C
makes sense! I wonder if all the answers here are 100% correct. I mean who answers them or votes for the correct answer?
upvoted 1 times
...
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Bechis
1 year, 7 months agozone9gardening
1 year, 6 months ago