Given below are different steps involved in the vulnerability-management life cycle.
1) Remediation
2) Identify assets and create a baseline
3) Verification
4) Monitor
5) Vulnerability scan
6) Risk assessment
Identify the correct sequence of steps involved in vulnerability management.

  • A. 2 ג†’ 5 ג†’ 6 ג†’ 1 ג†’ 3 ג†’ 4
  • B. 2 ג†’ 4 ג†’ 5 ג†’ 3 ג†’ 6 ג†’ 1
  • C. 2 ג†’ 1 ג†’ 5 ג†’ 6 ג†’ 4 ג†’ 3
  • D. 1 ג†’ 2 ג†’ 3 ג†’ 4 ג†’ 5 ג†’ 6
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Getaneh
Highly Voted 2 years, 5 months ago
The correct choice is: A. 2- 5- 6 -1 -3- 4 B. 2 -4 -5- 3 -6 -1 C. 2- 1 -5 -6 -4 -3 D. 1- 2 -3 -4 -5 -6 Correct answer is A: 2-5-6-1-3-4
upvoted 16 times
CHCHCHC
8 months, 1 week ago
correctomundo
upvoted 1 times
...
...
Daniel8660
Highly Voted 1 year, 6 months ago
Selected Answer: A
★Vulnerability- Management Life Cycle: 1.Identify Assets and Create a Baseline 2.Vulnerability Scan 3.Risk Assessment 4.Remediation 5.Verification 6.Monitor (P.515)
upvoted 9 times
...
Bengkel
Most Recent 1 year, 1 month ago
Selected Answer: B
B. 2- 5- 6 -1 -3- 4
upvoted 1 times
...
123toman123
1 year, 5 months ago
Selected Answer: B
B. 2- 5- 6 -1 -3- 4
upvoted 1 times
...
pinguin666
1 year, 9 months ago
identify assets vulnerability scan risk assessment remediation verification monitor page 499 in EC council material
upvoted 5 times
...
Qwertyzloy
2 years, 4 months ago
https://egs.eccouncil.org/wp-content/uploads/2020/12/Risk-and-Vulnerability-Assessment-Do-You-Know-the-Other-Side.pdf yeap, no correct answer. Correct is - 2 5 6 1 3 4
upvoted 1 times
...
Unitel21
2 years, 4 months ago
The answer is not here, it is supposed to be 2-5-6-1-3-4
upvoted 2 times
...
LIBUNB
2 years, 5 months ago
Mentioned answer is wrong. Correct answer is 2 5 6 1 3 4
upvoted 1 times
...
Osen
2 years, 6 months ago
Correct answer is: 2-5-6-1-3-4
upvoted 1 times
...
beowolf
2 years, 6 months ago
the answer options are encrypted ;)
upvoted 2 times
lawbut2
2 years, 5 months ago
Obfuscated using Stegonagraphy. ;)
upvoted 2 times
...
...
Q0ne
2 years, 6 months ago
The offcial course ppt shows the Vulnerability-Management Life Cycle is as follows: 2) Identify assets and create a baseline 5) Vulnerability scan 6) Risk assessment 1) Remediation 3) Verification 4) Monitor 2) Identify assets and create a baseline That is 2-5-6-1-3-4-2-5-6-1-3-4-2... So, NO CORRECT ANSWER HERE, Plz pay attention.
upvoted 4 times
...
Scryptic
2 years, 7 months ago
None of the answers are correct according to Page 516 EC-Council Course v11: Identify Assets and Create a Baseline Vulnerability Scan Risk Assessment Remediation Remediation Monitor Admittedly, I can't decipher what is printed exactly, but the number sequences don't line up.
upvoted 5 times
Scryptic
2 years, 7 months ago
Sorry about that, doubled up on one, and skipped the second, here is the corrected sequence: Page 516 EC-Council Course v11: Identify Assets and Create a Baseline Vulnerability Scan Risk Assessment Remediation Verification Monitor
upvoted 11 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago