Smith, the project manager for a larger multi-location firm, is leading a software project team that has 18 members, 5 of which are assigned to testing. Due to recent recommendations by an organizational quality audit team, the project manager is convinced to add a quality professional to lead to test team at additional cost to the project.
The project manager is aware of the importance of communication for the success of the project and takes the step of introducing additional communication channels, making it more complex, in order to assure quality levels of the project. What will be the first project management document that Smith should change in order to accommodate additional communication channels?

  • A. WBS document
  • B. Scope statement
  • C. Change control document
  • D. Risk management plan
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
johndoe69
4 months, 1 week ago
Selected Answer: C
Change Control Document: The introduction of a new team member (the quality professional) and the addition of new communication channels constitute changes to the project. The change control document outlines the process for managing changes to the project, including changes to the team structure, communication plans, and other project elements. This document should be updated first to formally acknowledge the change and describe how it will be managed. WBS (Work Breakdown Structure) document: While the WBS might eventually need to be updated to reflect the new team member's tasks, it is not the first document to change in response to the communication channel adjustment.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...