The primary purpose of a risk register is to:

  • A. Maintain a log of discovered risks
  • B. Track individual risk assessments
  • C. Develop plans for mitigating identified risks
  • D. Coordinate the timing of scheduled risk assessments
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://sitemate.com/us/resources/articles/safety/purpose-of-a-risk-register/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
BigMomma4752
3 weeks, 4 days ago
Selected Answer: A
The correct answer is A. Page 57 of the study guide.
upvoted 1 times
...
ImranNY
10 months, 3 weeks ago
The Answer C is also correct as the modern Risk Register is combination of both, keeping track of identified Risk, and the Mitigation Plan.
upvoted 1 times
...
ImranNY
10 months, 3 weeks ago
The answer A is debatable because the modern Risk Register not only maintains a log, but also has mitigation plans embedded in the Risk register.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago