As the CISO, you are the project sponsor for a highly visible log management project. The objective of the project is to centralize all the enterprise logs into a security information and event management (SIEM) system. You requested the results of the performance quality audits activity.
The performance quality audit activity is done in what project management process group?

  • A. Executing
  • B. Controlling
  • C. Planning
  • D. Closing
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
GeorgeForever
2 months, 2 weeks ago
Selected Answer: A
Executing Process Group Activity #10: Perform quality audits Quality audits are done during executing phase. This is for checking whether quality requirements of the project are met.
upvoted 1 times
...
alfaMegatron
2 months, 3 weeks ago
Selected Answer: A
During execution stage, the project team carries out the tasks defined in the project plan. A performance quality audit at this stage ensures that the project's deliverables meet the required quality standards. It involves reviewing work processes, checking for compliance with project specifications, and ensuring that the project's outputs are aligned with the expected quality.
upvoted 1 times
...
nshams
4 months, 2 weeks ago
Selected Answer: B
measuring result in control phase
upvoted 1 times
...
johndoe69
5 months, 2 weeks ago
Selected Answer: B
This is detailed in Chapter 8 of the PMBOK Guide, under the Control Quality process: Control Quality (Chapter 8.3): "The process of monitoring and recording results of executing the quality activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations."
upvoted 1 times
...
Ath3na89
5 months, 3 weeks ago
Selected Answer: B
The Controlling process group in project management is focused on monitoring and measuring project performance to identify any necessary changes to keep the project on track. This includes performance quality audits which are conducted to ensure that the project meets the defined performance standards, and that all parts of the project are being executed properly according to the project management plan.
upvoted 1 times
...
CYNLEE
1 year, 7 months ago
Selected Answer: A
Quality Audit is part of Quality Assurance activities under Executing Process Group oer PMBOK https://www.pmi.org/learning/library/practice-three-project-quality-management-7198
upvoted 2 times
...
Pika26
1 year, 8 months ago
B. Controlling The performance quality audit activity falls within the Controlling process group in project management. This process group focuses on monitoring and controlling project performance, ensuring that the project stays on track, and making any necessary adjustments to keep the project aligned with its objectives. Quality audits help to assess whether the project is following the defined processes, standards, and guidelines to achieve the desired level of quality.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...