Question #: 16
Topic #: 1
[All DES-2T13 Questions]

You are analyzing the performance data to avoid oversizing of a CI solution. What date and time frame should you use?

  • A. Average production time over multiple days
  • B. Peak production times over multiple days
  • C. Average production time over a single day
  • D. Peak production times over a single day
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JBONINO
3 years, 8 months ago
Verify the frequency and duration of the peaks to avoid over-sizing. Ensure to capture performance statistics during peak production times over multiple days. Correct B
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago