SRDF/Metro has been deployed between two data centers. SRDF/Metro is operating normally. Maintenance tasks at the R1 data center require the array to be offline.
Which SRDF operation should be executed on the Metro RDF pairs to facilitate the planned outage without affecting application I/O?

  • A. Failover
  • B. Split with bias set to R2
  • C. Suspend with bias set to R2
  • D. Swap
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Aveena91
4 years, 1 month ago
Correct answer C: For a planned SRDF outage, the suspend action is issued to take the device pairs out of the ActiveActive or ActiveBias RDF pair state.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago