A Dell PowerStore 9000X came online after being initially configured seven days ago. The manager UI shows capacity but no forecasting metrics.

Why are forecasting metrics not being displayed?

  • A. Forecasting was not turned on during configuration.
  • B. The capacity forecasting license must be installed.
  • C. There is not enough capacity in the appliance.
  • D. Forecasting will not display until 16 days after initial configuration.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ronaldvs
1 year, 6 months ago
Selected Answer: D
Forecasting metrics will not display in the PowerStore Manager UI until 16 days after initial configuration.
upvoted 1 times
...
jakesles
1 year, 7 months ago
Selected Answer: D
Capacity monitoring and forecasting require at least a 15-day runtime in order to fully predict capacity statistics. Runtime starts when the appliance comes online after initial configuration. On the 16th day, you should see forecast metrics being reported in PowerStore Manager or REST API.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago