Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?

  • A. EAC
  • B. BAC
  • C. CPI
  • D. ETC
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 2 months ago
C The metric that demonstrates if a project is overspending or underspending is the Cost Performance Index (CPI).
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago