The NEXT step after justifying a required change with the associated impact on the project is B. Approval.
After the project manager has identified and evaluated the impact of the required change, the next step is to seek approval from the relevant stakeholders. This may include obtaining formal approval from a change control board, project sponsor, or other decision-making body before proceeding with implementation.
Once the change is approved, the project manager can move forward with implementation and validation to ensure that the change has been successfully incorporated into the project. Auditing may be conducted later in the project to assess the effectiveness of the change and identify areas for improvement.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CyberRooster
2 years, 2 months ago