Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Choose two.)

  • A. Planned value
  • B. Schedule variance
  • C. Acceptable variance
  • D. Cost variance
  • E. Earned value
Show Suggested Answer Hide Answer
Suggested Answer: DE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 2 months ago
Why not Schedule Variance and Cost Variance? Can someone please explain?
upvoted 3 times
NextTopic
2 years ago
I'm thinking the same
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago