A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time. Which of the following techniques is MOST likely to be used to complete the project on time?
Crashing is a technique that looks at cost and schedule trade-offs. Crashing is typically
implemented by adding more resources to the critical path tasks in order to complete the
project more quickly. Crashing can also be accomplished by requiring mandatory
overtime for those team members working on critical path tasks or by speeding up
delivery times from team members, vendors, and so on.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
sedative
2 years, 2 months ago