A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.
Which of the following techniques is MOST likely to be used to complete the project on time?

  • A. Throttling
  • B. Crashing
  • C. Resource leveling
  • D. Resource smoothing
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sedative
2 years, 2 months ago
Crashing is a technique that looks at cost and schedule trade-offs. Crashing is typically implemented by adding more resources to the critical path tasks in order to complete the project more quickly. Crashing can also be accomplished by requiring mandatory overtime for those team members working on critical path tasks or by speeding up delivery times from team members, vendors, and so on.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago