exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 38 discussion

Actual exam question from CompTIA's PK0-004
Question #: 38
Topic #: 1
[All PK0-004 Questions]

The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.
Which of the following should the project manager do to obtain the resources?

  • A. The project manager should identify and document the reasons for the additional resources in a change request.
  • B. The project manager should hire additional resources temporarily to complete the project.
  • C. The project manager should terminate the project until additional resources are added to the project.
  • D. The project manager should ask the project team members to take on more tasks to complete the project on time.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 2 months ago
A. The project manager should identify and document the reasons for the additional resources in a change request. When the project sponsor reduces the resources required for project completion, it could lead to project delays or inability to complete the project. The project manager should document the reasons why additional resources are required in a change request and submit it to the project sponsor for approval. The change request should include the impact on the project schedule, cost, scope, and any other relevant factors. This allows the project sponsor to review the request and make an informed decision based on the project's priority and available resources.
upvoted 1 times
...
rpecana
2 years, 3 months ago
Selected Answer: A
Quizlet: A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago