exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 34 discussion

Actual exam question from CompTIA's PK0-004
Question #: 34
Topic #: 1
[All PK0-004 Questions]

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

  • A. SCRUM retrospective
  • B. Kickoff meeting
  • C. Budget baseline
  • D. Risk review
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 2 months ago
A. SCRUM retrospective is typically conducted at the end of each iteration in an iterative approach. SCRUM is an iterative framework for managing projects, and a retrospective is an essential ceremony that takes place at the end of each sprint or iteration. During the retrospective, the team reflects on the previous sprint and discusses what went well, what could have gone better, and what changes they can make to improve the next sprint. By continuously reviewing and adapting, the team can ensure that they are making progress toward their goals and delivering value to the customer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago