Question #: 598
Topic #: 1
[All PK0-004 Questions]

A project manager is reviewing a project's status and finds that while it is 25% under budget, there are significant quality defects, and the project is behind by six weeks.
Which of the following should the project manager increase to BEST resolve this issue?

  • A. Resources
  • B. Quality
  • C. Schedule
  • D. Scope
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Resources on a project schedule typically refer to human resources and/or consulting or contracting resources who will work on the tasks.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TreeeSon
2 years, 1 month ago
This question is extremely ambiguous. CompTIA could be tricking me but I believe it's B. They are already behind schedule, but increasing it doesn't address the quality issue which is most likely going to cause issues in the long run. While the budget is under it seems increasing the quality can help. However, it is confusing cause is the core problem the defects or the schedule? What issue are we trying to resolve?!
upvoted 1 times
...
kmanb
2 years, 3 months ago
Selected Answer: C
C. Schedule It appears that the project is behind schedule, and increasing the schedule may help to resolve this issue. The project manager may need to consider adding additional resources or adjusting the scope of the project in order to get back on track. It is also important to address the quality issues that have been identified, as these can impact the overall success of the project. However, increasing the focus on quality may not necessarily help to get the project back on schedule, so it is important to address the root cause of the schedule delay in order to resolve the issue effectively.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.