The sponsorship of an active project has changed multiple times, and stakeholders have submitted a large number of change requests. Which of the following would be the BEST method to rebaseline the project?
Rebaselining a project involves updating the project's baseline plan, which may be necessary due to changes in the project's scope, schedule, or budget. In this scenario, since the sponsorship of the active project has changed multiple times, and stakeholders have submitted a large number of change requests, a detailed status report would be the most appropriate method to rebaseline the project.
The best method to rebaseline the project in this situation would be a mandatory meeting. A mandatory meeting is a meeting that all project team members are required to attend, and it is an appropriate forum for discussing and resolving issues related to the project. In a mandatory meeting, the project team can review the change requests that have been submitted, assess the impact of these changes on the project, and agree on a plan for rebaseling the project.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MJVIS
2 years, 2 months agokmanb
2 years, 3 months ago