exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 731 discussion

Actual exam question from CompTIA's PK0-004
Question #: 731
Topic #: 1
[All PK0-004 Questions]

A project team is ready to start working on a project; however, the project manager says the work needs to be planned first. Which of the following is MOST likely to be produced during the first planning workshop?

  • A. Gantt chart
  • B. RACI
  • C. WBS
  • D. Risk register
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 2 months ago
Selected Answer: C
During the first planning workshop, the project team will work together to develop a plan for the project. One of the first steps in this process is typically to develop a Work Breakdown Structure (WBS), which is a hierarchical decomposition of the project into smaller, more manageable components. The WBS provides a framework for organizing the project work, and it can help the team to identify the major deliverables and activities that will be required to complete the project. It is often used as a basis for developing the project schedule, budget, and other project management plans. Therefore, the most likely output from the first planning workshop would be the WBS. The other options, such as the Gantt chart, RACI, and risk register, are all important project management tools that will be developed later in the planning process, once the WBS and other key project plans are in place.
upvoted 1 times
...
kmanb
2 years, 3 months ago
Selected Answer: C
A work breakdown structure (WBS) is most likely to be produced during the first planning workshop
upvoted 2 times
...
MJVIS
2 years, 4 months ago
Selected Answer: C
Why it's not WBS?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago