A project team is ready to start working on a project; however, the project manager says the work needs to be planned first. Which of the following is MOST likely to be produced during the first planning workshop?
During the first planning workshop, the project team will work together to develop a plan for the project. One of the first steps in this process is typically to develop a Work Breakdown Structure (WBS), which is a hierarchical decomposition of the project into smaller, more manageable components.
The WBS provides a framework for organizing the project work, and it can help the team to identify the major deliverables and activities that will be required to complete the project. It is often used as a basis for developing the project schedule, budget, and other project management plans.
Therefore, the most likely output from the first planning workshop would be the WBS. The other options, such as the Gantt chart, RACI, and risk register, are all important project management tools that will be developed later in the planning process, once the WBS and other key project plans are in place.
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MJVIS
2 years, 2 months agokmanb
2 years, 3 months agoMJVIS
2 years, 4 months ago