The project manager for a TV tower construction project receives notification that a strong storm is expected the following week. Which of the following should the project manager do NEXT?
A.
Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
B.
Evaluate the risk, fill in the issue log, and communicate it according to the communication plan.
C.
Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
D.
Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
Always develop a plan of action first, before making changes or notifying stakeholders. Remember - stakeholders want you to come with them with the problem AND the solution, not just the problem. Their time is valuable.
The answer is
C. Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
The communication plan will include contacting stakeholders. AFTER the plan of action is in place, of course.
upvoted 1 times
...
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
hayo
2 years, 4 months agoLee_Lah
2 years, 2 months ago