exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 22 discussion

Actual exam question from CompTIA's PK0-004
Question #: 22
Topic #: 1
[All PK0-004 Questions]

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.
Which of the following should a project manager update to document this information?

  • A. A list of realized risks
  • B. A list of decomposed activities
  • C. A sequenced list of project tasks
  • D. A document describing agreed-upon communication methods
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 2 months ago
A. A project manager should update a list of realized risks to document this information. A risk is an uncertain event or condition that, if it occurs, can have a positive or negative effect on the project's objectives. A realized risk is a risk that has occurred and is impacting the project. In this case, the unavailability of the datacenter and the absence of the team member assigned to complete the datacenter project are both realized risks that need to be documented. By updating the list of realized risks, the project manager can keep track of the risks that have occurred and their impact on the project. This will help the project manager to manage the project's constraints and make informed decisions to minimize the risks' impact. The project manager can also update the risk response plan to address these realized risks and mitigate their impact on the project.
upvoted 1 times
...
user82
2 years, 4 months ago
Can someone explain what a "realized risk" is? I don't see it anywhere in CompTIA's study guide and the page references are always incorrect.
upvoted 1 times
hayo
2 years, 4 months ago
Its when a risk event actually happens.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago