A project must be:

  • A. continuous.
  • B. budgeted.
  • C. unique.
  • D. complex.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CertoHolic
2 years, 1 month ago
Selected Answer: C
Project should be unique
upvoted 1 times
...
matts5150
2 years, 3 months ago
Selected Answer: C
The answer is C
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: C
The answer is C according to comptia
upvoted 2 times
...
Bruce1
2 years, 5 months ago
The answer is C. Project is unique.
upvoted 2 times
...
all4one
2 years, 5 months ago
According to the comptia objectives, the projects must be temporary, have start to finish dates and should be unique.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago