Exam 220-1102 topic 1 question 76 discussion

Actual exam question from CompTIA's 220-1102
Question #: 76
Topic #: 1
[All 220-1102 Questions]

A change advisory board did not approve a requested change due to the lack of alternative actions if implementation failed. Which of the following should be updated before requesting approval again?

  • A. Scope of change
  • B. Risk level
  • C. Rollback plan
  • D. End user acceptance
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Dido1963
Highly Voted 1 year, 1 month ago
Selected Answer: C
if implementation failed you need a rollback plan
upvoted 7 times
...
Skydragon207
Most Recent 1 month ago
where can I find all the steps of change advisory?
upvoted 1 times
...
DMC71
6 months, 2 weeks ago
Is reimagining the same as reformatting?
upvoted 1 times
...
Delawasp
7 months, 1 week ago
Selected Answer: C
C. Rollback plan should be updated before requesting approval again. If the change advisory board did not approve a requested change due to the lack of alternative actions if implementation failed, then updating the rollback plan would be the logical next step. A rollback plan outlines the steps to be taken if the change does not produce the desired results or causes problems in the system. By updating the rollback plan, the requester can provide the change advisory board with a clear understanding of how they plan to address issues that may arise if the change is implemented. Updating the scope of change, risk level, or end user acceptance may also be necessary, but they are not directly related to the issue of lack of alternative actions in case of failure.
upvoted 3 times
...
rah555
9 months, 2 weeks ago
Selected Answer: C
A rollback plan is a contingency plan that outlines the steps that will be taken if a change fails or causes problems.
upvoted 3 times
...
examreviewer
10 months, 1 week ago
Selected Answer: C
C. Rollback plan If a change advisory board did not approve a requested change due to the lack of alternative actions if implementation failed, the rollback plan should be updated before requesting approval again. A rollback plan outlines the steps that will be taken to undo the changes if the implementation fails or causes unexpected issues. The scope of change, risk level, and end-user acceptance may also need to be updated if they are found to be insufficient, but they are not directly related to the lack of alternative actions in case of implementation failure. Updating the rollback plan can help provide assurance to the change advisory board that appropriate measures are in place to mitigate the risks associated with the change.
upvoted 2 times
...
[Removed]
1 year ago
Selected Answer: C
C, it says failed due to lack of alternative options. So c is the answer.
upvoted 4 times
...
alexandrasexy
1 year, 1 month ago
Selected Answer: B
B. Risk level
upvoted 1 times
...
simsbow1098
1 year, 3 months ago
Selected Answer: B
The answer should be B.
upvoted 2 times
minx98
10 months, 3 weeks ago
hahaha this guy's gonna fail
upvoted 1 times
...
Jackybro
1 year, 3 months ago
I don't think so. The question says "lack of options if implementation fails", which is the literal definition of a backout plan.
upvoted 6 times
LayinCable
9 months, 3 weeks ago
But he's saying its Risk Level, not Rollback Plan. Risk level is B.
upvoted 2 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago