Which of the following documents would a project manager utilize to find a vendor for an undefined project?

  • A. RFP
  • B. RFI
  • C. RFQ
  • D. SOW
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Manzer
2 years, 7 months ago
Selected Answer: B
disseminates a Request for Information (RFI), they are seeking general information about prospective suppliers' capabilities and services/goods.
upvoted 3 times
all4one
2 years, 5 months ago
RFP is correct. RFI A formal request from the buyer to the seller for additional information about goods and services the seller may provide. It’s not an official sign of business to come but is often a starting point of research to start the procurement processes. A formal request from your company to a prospective vendor or vendors to create a proposal for the work to be completed and provide you with a cost estimate. An RFP does not guarantee anyone the job; it simply formalizes the proceedings of the selection process.
upvoted 1 times
TreeeSon
2 years, 1 month ago
The source even says that the project is defined for RFP the question clearly states undefined. Im going to agree with Manzer.
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago