exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 224 discussion

Actual exam question from CompTIA's PK0-004
Question #: 224
Topic #: 1
[All PK0-004 Questions]

A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of the following should the project manager do NEXT?

  • A. Determine the expected duration of the rework and complete a charge request to modify the project baselines.
  • B. Notify the project sponsor to schedule and facilitate a team meeting to rework the design documentation.
  • C. Determine the expected duration of the rework with any associated quality control activities and add the duration to an updated version of the WBS.
  • D. Update the master project schedule, and distribute it all stakeholders in accordance with the project communications plan.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 1 month ago
I think it's C. Determine the expected duration of the rework with any associated quality control activities and add the duration to an updated version of the WBS. Before taking any action, the project manager should determine the expected duration of the rework, including any additional quality control activities that may be necessary. This will allow for a more accurate schedule update and prevent further delays. Once the expected duration of the rework has been determined, it should be added to an updated version of the WBS to reflect the changes in the project schedule. Updating the master project schedule and distributing it to stakeholders should be done after the necessary updates have been made to the WBS.
upvoted 1 times
...
Braniac
2 years, 7 months ago
A says "charge request"... not relevant. answer is ;
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel