To facilitate product testing, an outside vendor was contracted to provide resources for project completion. Each resource will be given network and door access.
The outside vendor has provided background checks for all the resources. Which of the following should the project manager request from the outside vendor prior to providing access rights for these resources?
MJVIS
2 years, 2 months agobrvndvnwolf
2 years, 5 months agoCoinUmbrella
2 years, 6 months agoCoinUmbrella
2 years, 6 months agoBruce1
2 years, 6 months agoChambone
2 years, 6 months agoSutokuto
2 years, 7 months ago