Question #: 810
Topic #: 1
[All PK0-004 Questions]

Based on the information below:

AC=100 -

SV=80 -

EV=120 -
Which of the following is the CPI of the project?

  • A. 0.8
  • B. 0.83
  • C. 1.2
  • D. 1.25
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
djfinwne
Highly Voted 2 years, 7 months ago
C. 1.2 CPI=EV/AC
upvoted 7 times
...
jksdbfb
Highly Voted 2 years, 7 months ago
Selected Answer: C
The answer is C
upvoted 6 times
...
MJVIS
Most Recent 2 years, 1 month ago
Why is no one updating the correct answers? This is very confusing. The answer is 1.2 but the website is still showing the incorrect answer. What is the purpose of this discussion board?
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: C
C. 1.2 120/100=1.2
upvoted 1 times
...
Jad11
2 years, 5 months ago
Selected Answer: C
The answer is C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago