The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?
D
Estimating the work package should be done after the project team has identified all the tasks needed to create the project deliverables and grouped them into work packages covering all project scope.
A work package is a group of related tasks that are identified and planned together as a single unit of work. Once the work packages have been identified, the next step is to estimate the effort and duration required to complete each work package.
The Work Package has been completed (according to the question). The next step is to identify the relationships between activities.
Source: CompTIA Student Guide PK0-004 Edition 2.0
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
joe99999
2 years, 1 month agobrvndvnwolf
2 years, 5 months agoDomdom120
2 years, 9 months ago