Which of the following is the BEST indicator of project failure?

  • A. Product deficiencies revealed during the monitor and control phase
  • B. Project team members disagreeing on milestones
  • C. Project deliverables completed behind schedule
  • D. Several changes being made to the project
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
joe99999
2 years, 1 month ago
A: is supposed to help avoid a failure. Product deficiencies do not necessarily represent project failure, but they require careful monitoring, identification, and corrective action to ensure that the project delivers a high-quality product that meets the stakeholders' needs and requirements. C: Doesn't always mean a project failure. A common indicator of project failure include: Missed deadlines: If a project consistently misses deadlines or is significantly delayed, it may be an indication of poor planning or inadequate resources. In this case C: should be the BEST answer.
upvoted 1 times
...
MJVIS
2 years, 2 months ago
Selected Answer: C
C. Project deliverables completed behind schedule is the BEST indicator of project failure. While each of the options listed could be a potential problem for a project, completing project deliverables behind schedule is the most significant and critical indicator of project failure. Meeting project timelines is a fundamental measure of project success, and delays in project completion can lead to cost overruns, missed opportunities, and loss of stakeholder trust. In contrast, product deficiencies, disagreements among team members, and changes to the project are all issues that can be addressed and resolved through effective project management practices, provided that the project stays on schedule. However, falling behind schedule can impact all aspects of the project, making it much more challenging to achieve success and meet stakeholder expectations.
upvoted 1 times
TreeeSon
2 years, 1 month ago
MJVIS have you taken the exam yet? You mind contacting me?
upvoted 1 times
...
...
Geodude
2 years, 4 months ago
Selected Answer: D
I am thinking its D here. To me having to make multiple changes to a project means that the whole thing was not planned correctly and it has failed.
upvoted 1 times
...
all4one
2 years, 7 months ago
Is A the correct answer? why?
upvoted 1 times
...
[Removed]
2 years, 9 months ago
On-time Delivery Any project that is late is considered a failure. Organizations in highly competitive, time-to-market driven industries are sometimes tolerant of cost overruns as long as a project meets its target launch date.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago