exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 512 discussion

Actual exam question from CompTIA's PK0-004
Question #: 512
Topic #: 1
[All PK0-004 Questions]

A project manager is collecting work package information from the project team for the first time.
Which of the following elements should the project manager have at the end of the meeting?

  • A. Task name, duration, and dependencies
  • B. Task leveling, baseline, and critical path
  • C. Task assignments, quality requirements, and project governance sign-off
  • D. Task start, finish, and estimate cost
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
wisut
Highly Voted 2 years, 10 months ago
Selected Answer: A
"for the first time" should be simple thing
upvoted 6 times
...
MJVIS
Most Recent 2 years, 2 months ago
Selected Answer: A
A. Task name, duration, and dependencies should be collected by the project manager at the end of the meeting when collecting work package information from the project team for the first time. Task name, duration, and dependencies are essential elements of a work package. They are critical for understanding what work needs to be done, how long it will take, and what tasks must be completed before others can begin. Without this information, it would be difficult to manage the project timeline, assign resources, or identify potential roadblocks.
upvoted 1 times
...
CoinUmbrella
2 years, 6 months ago
Selected Answer: D
During planning, project work is broken down into work packages and activities. Each work package is assigned a budget and schedule. Because each increment of work is time-phased, a Schedule Variance (SV) results when work is not completed as scheduled. It is always better to understand the monetary value of work contribution as it relates to the schedule. Therefore, SV is often expressed in terms of the monetary value.
upvoted 1 times
...
Manzer
2 years, 7 months ago
Selected Answer: C
The work package can also be described as manageable work effort, or a level at which the cost and schedule for the work can be easily estimated.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago