A project team is defining detailed risks. Which of the following project phases is taking place?

  • A. Initiation
  • B. Monitor and control
  • C. Execution
  • D. Planning
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 2 months ago
Selected Answer: D
In the Planning processes, the project goals, objectives, and deliverables are refined and broken down into manageable units of work. Project managers create time and cost estimates and determine resource requirements for each activity. Planning involves several other critical areas of project management, including communication, risk, human resources, quality, and procurement. The key activities in the Planning process group are as follows: Develop a project schedule. Create a work breakdown structure. Determine resources. Identify and plan for detailed risks. Determine project requirements. Write a communication plan. Develop a procurement plan if utilizing resources outside the organization. Develop a change management plan. Define the project budget. Reference Comptia Kim Heldman Page-103
upvoted 1 times
...
Braniac
2 years, 7 months ago
Think its D because the RBS is created during that phase. which is a detailed layout of risks.
upvoted 1 times
...
scouttyper
2 years, 10 months ago
High level risk are in the Initiation stage, detailed risks are in the Planning Stage
upvoted 3 times
...
boooliyooo
3 years, 1 month ago
Selected Answer: C
It varies since risks are identified progressively, and being detailed is unlikely to be done in planning stage
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago