Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer.
Which of the following is the MOST likely impact to Project B?

  • A. The cost will increase.
  • B. There will be no impact.
  • C. The scope will change.
  • D. The schedule will change.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
papahawaii
2 years, 1 month ago
Selected Answer: B
Allocated buffer = no impact to actual project, as the buffer is there.
upvoted 1 times
...
all4one
2 years, 5 months ago
Selected Answer: A
I would say the cost will increase. Any type of rework should increase the cost.
upvoted 1 times
...
Treymb6
3 years, 1 month ago
Selected Answer: B
I am leaning towards B for this one since it says "to be done in the allocated buffer". If there is an allocated buffer, then there shouldn't be any sort of impact.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago