Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?

  • A. Project manager and project scheduler
  • B. Project coordinator and project sponsor
  • C. Project champion and project scheduler
  • D. Project stakeholders and project team
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TreeeSon
2 years, 1 month ago
From ChatGPT: D. Project stakeholders and project team are the most likely target audience to be notified of the achievement of a key milestone in a project schedule. Project stakeholders are individuals or groups who have an interest in the project and can affect or be affected by its outcomes, while the project team includes all individuals who are working on the project. It is important to keep the stakeholders informed about the progress of the project, including the achievement of key milestones, to ensure they remain engaged and supportive throughout the project's lifecycle.
upvoted 1 times
...
Braniac
2 years, 7 months ago
B. Project Managers supply the notification of milestones to Sponsors, Clients, and potentially Senior Management in a Dashboard. This is essentially a trigger. And the project team receives alerts for Audits, Stakeholder changes, incident responses, and also detailed items specific to their tasks only. Furthermore, Project stakeholders is vague, and could be referring to the project team in regard to all stakeholders. Champion is equivalent to sponsor But the project scheduler is the one who knows whats happening... Because he created the schedule, so why would you update the guy who is just gonna be like, I know. In the absence of a Project Manager, the Project Coordinator takes on more responsibility when making time - and - resource scheduling decisions. So considering the sponsor is already to be alerted, the project coordinator is a reasonable second choice for the Update. its B.
upvoted 1 times
...
Anthony053
3 years, 1 month ago
D. Project stakeholders and project team -Changes must be communicated to team members, project sponsor, and project stakeholder.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago