Question #: 93
Topic #: 1
[All N10-008 Questions]

A company requires a disaster recovery site to have equipment ready to go in the event of a disaster at its main datacenter. The company does not have the budget to mirror all the live data to the disaster recovery site. Which of the following concepts should the company select?

  • A. Cold site
  • B. Hot site
  • C. Warm site
  • D. Cloud site
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sharribear
Highly Voted 2 years, 8 months ago
Selected Answer: C
A Warm Site would have hardware already in place, just need to bring software. Less expensive than a Hot Site
upvoted 21 times
...
StevenElev11n
Highly Voted 1 year, 8 months ago
Selected Answer: C
A cold site is a backup facility with basic infrastructure but no IT equipment, which takes time to get up and running in the event of a disaster. A hot site is a backup facility with all necessary IT systems and equipment ready for immediate use but is more expensive to maintain. A warm site is between a cold and hot site, having some pre-installed IT systems and equipment, but still requiring effort to get up and running in the event of a disaster.
upvoted 10 times
...
Knight82
Most Recent 6 months, 4 weeks ago
Cloud is more cost effective than warm and hot. No?
upvoted 1 times
...
Mehsotopes
11 months, 3 weeks ago
Selected Answer: C
Warm Site = Restoral time between 24 hours & seven days (under a week). = An available building that already contains a lot of the equipment. With this equipment, you may not have the latest security patches, or even the data backups from your other site have not been recovered yet, but at least have the hardware & cabling. This holds your switches, routers, & firewalls .
upvoted 1 times
...
comeragh
1 year, 1 month ago
Selected Answer: C
C - warm site correct
upvoted 1 times
...
Ahmad_
2 years, 2 months ago
The correct answer is Hot Site
upvoted 1 times
fouserd
1 year, 11 months ago
Incorrect - Hot site would mean they have a 1 to 1 with equipment, networking, application/software.
upvoted 10 times
...
...
Pongsathorn
2 years, 6 months ago
Selected Answer: C
A warm site is a leased facility that contains electrical and communications wiring, full utilities, and networking equipment. In most cases, the only thing that needs to be restored is the software and the data. A warm site takes longer to restore than a hot site but less than a cold site.
upvoted 4 times
...
itssnowyseason
2 years, 6 months ago
Why wouldn't it be B since it said it can't mirror and a hot site mirrors.
upvoted 1 times
hypertweeky
2 years, 5 months ago
It doesn’t have the budget to mirror.. A hot site is the most expensive option. Hence, warm is the better option since cold site is just the building itself with electricity and HVAC system.
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago