The management team has instituted a 48-hour RTO as part of the disaster recovery plan. Which of the following procedures would meet the policy's requirements?
A.
Recover all systems to a loss of 48 hours of data.
B.
Limit the network downtime to a maximum of 48 hours per year.
Option C: Recover all systems within 48 hours.
RTO stands for Recovery Time Objective, which is the maximum allowable downtime or duration of a service outage after a disaster or disruption. It means how long it will take to recover the system or service to normal operations after a disaster or incident.
In this case, the management team has set a 48-hour RTO, which means that all critical systems should be fully operational within 48 hours after a disaster occurs. Option C is the only answer that aligns with the policy's requirements, as it explicitly states the goal of recovering all systems within the required time frame.
RTO means Recovery Time Object and than answer make sense..
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.N10-007 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
StellarSteve
2 years, 1 month agomarerad
3 years, 2 months ago