exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 31 discussion

Actual exam question from CompTIA's PK0-004
Question #: 31
Topic #: 1
[All PK0-004 Questions]

After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?

  • A. Use milestones identified in the project charter.
  • B. Use data based on past knowledge.
  • C. Hold a full team workshop to review the complete WBS.
  • D. Collaborate with other project managers.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
6phaeton
2 years ago
Selected Answer: B
The project manager can leverage past project experience, historical data, and benchmarks to determine the initial sequence and duration of project tasks. This is known as analogous estimating, which is a top-down estimation technique that uses actual durations and costs from past similar projects as a basis for estimating the duration and cost of the current project. This method can provide an initial estimate of project schedule and can help the project manager identify critical path activities. However, the project manager should also consider other factors, such as team availability, resource constraints, and risks, when developing the project schedule.
upvoted 1 times
...
ramrod1738
2 years, 2 months ago
C. Hold a full team workshop to review the complete WBS. The best way for the project manager to determine the initial sequence and durations is to hold a full team workshop to review the complete Work Breakdown Structure (WBS). The team members who will be responsible for executing the tasks are likely to have the most knowledge and experience with the specific tasks, so it is important to involve them in the planning process. During the workshop, the team can collaborate to identify any dependencies between tasks and determine the most logical sequence for completing the work. They can also estimate the duration of each task based on their experience and knowledge.
upvoted 1 times
...
Born_Again
3 years, 1 month ago
stands to reason that using milestones lets you know how far you need to go and how far you have traveled through your project.
upvoted 1 times
...
Doscar
3 years, 5 months ago
Why A?
upvoted 1 times
Insamity
3 years, 1 month ago
Milestones act as major events that can be used to determine the sequencing and durations between milestones.
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago