A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

  • A. Add durations.
  • B. Add the start and finish dates
  • C. Add tasks.
  • D. Add resources.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rpecana
2 years, 2 months ago
Selected Answer: C
- pg70 CompTIA Project+ Cert Guide
upvoted 1 times
...
Born_Again
3 years, 1 month ago
Selected Answer: C
Developing the project schedule Let’s look at the road so far. First, you created a task list and milestones by decomposing the work packages in your WBS. Then, you sequenced activities based on dependencies and relationships. After which, you estimated your resources and durations, taking into consideration dates, and effort, lead, and lag time, along with those estimates for the duration of the tasks. Now, we have a schedule. What we don’t have is a finish date, a total duration, and the answer to the question of how long it will take. That brings us to schedule creation. There are several techniques we will go through and I’m sure you have noticed that time management takes a lot of time to review!
upvoted 1 times
brown705
2 years, 9 months ago
What is it you are going to schedule? TASKS. You have to know what it is you are scheduling.
upvoted 1 times
...
...
boooliyooo
3 years, 1 month ago
After breaking the project into its individual components and documenting them in the WBS, the project manager can use the WBS to schedule all project activities. Creating the schedule is probably one of the most time-consuming tasks for any project because of the amount of coordination required in the process: 1. Determine the tasks. 2. Determine the project’s milestones. 3. Determine each task’s durations and start/finish dates. 4. Set predecessors and dependencies. 5. Sequence and prioritize the tasks. 6. Determine the critical path. 7. Allocate project resources to the individual tasks. 8. Set the schedule baseline. 9. Set the quality gates. 10. Set the governance gates. - pg70 CompTIA Project+ Cert Guide
upvoted 3 times
NextTopic
2 years ago
While I agree the answer is C. i'm using a sybex book (study guide pk0-004 2nd Ed) that arranges this list differently.. for instance: 1. Determine the tasks. 2. Sequence 3. allocate the resources 4. Determine each task’s durations and start/finish dates. 5. Determine the project’s milestones. 6. construct the schedule 7. Determine the critical path. 8. set baseline & obtain approval 9. Set the quality gates 10. Set/establish the governance gates. Which one should I follow?
upvoted 1 times
...
...
Hashlife
3 years, 5 months ago
Selected Answer: B
Wouldn't it be B?
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago