Exam PK0-004 topic 1 question 499 discussion

Actual exam question from CompTIA's PK0-004
Question #: 499
Topic #: 1
[All PK0-004 Questions]

Team members in a projectized organization are released at the end of a project and placed on the `bench`. Which of the following should the benched team members do NEXT?

  • A. Find a new project.
  • B. Check in with a functional manager.
  • C. Report to the project manager.
  • D. Contact the project sponsor.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
blah111
Highly Voted 3 years, 5 months ago
how can they check with functional manager in projectized organization?
upvoted 6 times
...
NextTopic
Most Recent 1 year, 11 months ago
I would say A, because the project manager would be looking for a new project as well. If anything they both should report to the PMO.
upvoted 1 times
...
joe99999
2 years, 1 month ago
B In a projectized organization, team members are typically managed by a project manager while they are working on a project. However, when team members are released at the end of a project and placed on the "bench," their management and reporting structure may change. In some cases, benched team members may report to a functional manager or a resource manager who is responsible for overseeing staffing and resource allocation for the organization. In this case, it would be appropriate for benched team members to check in with the functional manager to discuss their status, availability, and potential project opportunities.
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: C
Answer is C. report to PM
upvoted 1 times
...
[Removed]
2 years, 9 months ago
Typically, functional managers do not exist in Projectized Organizational Structures. If there is one, his power or authority is very limited. Organizations give project managers authority and power as needed to complete the project but this does not mean that he has absolute authority to do everything he wants. The resource would report to the PM to be reassigned
upvoted 2 times
...
spoiledsalsa
2 years, 10 months ago
Selected Answer: C
In projectized organizations, the PM calls the shots. The resources work for the PM. These resources belong to the PM's project alone and has authority. A drawback is that the team needs to know "what next" at the end of the project. This can cause a little anxiety for my team.
upvoted 1 times
...
blah111
3 years, 5 months ago
answer is A, find new project
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.