A team member has reported Task 3 will be completed ahead of schedule. Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?
If confused. Understand there is no definitive float or lag, so just pay attention to the start dates. Even if it takes one day less. task 4 still doesn't start until the 10th regardless of the previous task. unless this is determined to be an unnecessary gap and is remediated with a schedule update.
There is no change. Task 2 is the critical path task, whether or not Task 3 gets completed earlier is irrelevant, since Task 2 and 3 begin on the same day and Task 3 holds the longer duration.
its 12 days. If you move back task 3 one day on the chart it will move back task 4 one day and task 5 one day right? That will move back task 5 into the weekend making you wait until the 20th to start task 5 anyway so there is no change
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
PenguPC
Highly Voted 3 years, 7 months agoproject_tester
3 years, 7 months agoNextTopic
Most Recent 2 years agoBraniac
2 years, 7 months agoDomdom120
2 years, 9 months agoRob0645
3 years ago