Question #: 5
Topic #: 1
[All PK0-004 Questions]

A project manager is creating the WBS.
In which of the following phases is the project?

  • A. Initiation
  • B. Planning
  • C. Execution
  • D. Closing
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ramrod1738
2 years, 2 months ago
The project is in the Planning phase when the project manager is creating the Work Breakdown Structure (WBS). In the Initiation phase, the project is just starting, and the project manager is defining the scope and objectives of the project. In the Execution phase, the project manager is carrying out the work defined in the project plan, including implementing the WBS. In the Closing phase, the project manager is wrapping up the project, including completing any remaining work, conducting a final review, and closing out the project.
upvoted 1 times
...
cepojo
2 years, 2 months ago
Selected Answer: B
Correct B. WBS is created in the planning stage.
upvoted 1 times
...
4007
3 years, 10 months ago
B. The WBS is one of the key documents created at the end of the Planning phase.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago