Question #: 382
Topic #: 1
[All 220-1002 Questions]

A technician needs to update the network firewall, which will cause a temporary outage. The technician submits a change management request to perform the required maintenance. Which of the following provides details about what the technician will need to do if the update fails?

  • A. Back-out plan
  • B. Scope of the change
  • C. Risk analysis
  • D. End-user acceptance
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Renbrand
Highly Voted 3 years, 10 months ago
Probably rather A
upvoted 17 times
ep0ch
3 years, 5 months ago
I agree. The risk analysis would provide what could go wrong. The back-out plan would provide what to do if something goes wrong.
upvoted 1 times
...
iLikeBeagButt
2 years, 11 months ago
Definitely A...it's exactly what a backout plan is for, if something goes wrong... what do you do?
upvoted 1 times
...
giftedhands
3 years, 9 months ago
A is the correct answer. The technician would fall back on Back-out plan if anything goes wrong.
upvoted 5 times
...
...
ZioPier
Most Recent 1 year, 10 months ago
Selected Answer: A
Risk analysis provides details about how the change could affect the system and eventually downtime. Definitely, the details regarding actions to take in case of problems are in the backout plan.
upvoted 1 times
...
tomoige
2 years, 7 months ago
Selected Answer: A
This website is trying to sabotage me
upvoted 1 times
...
iLikeBeagButt
2 years, 11 months ago
Selected Answer: A
A. Back-out plan
upvoted 3 times
...
Alex1313
3 years, 7 months ago
"All changes to infrastructure come with risk. A proper change management request will certainly require a risk analysis, a detailed assessment of possible problems that could result from the change. >>> What if the upgrade fails? <<< Has the new application been tested on a sample system?" By Mike Meyers' book. So, ti seems that "C" is indeed right since risk analysis contains the details of a possible failure.
upvoted 3 times
redheadITgirl
3 years, 7 months ago
I see what you are reading from Mike Myers book. But the way this question is written "Provide details of what will the technician need to do if the update fails?" In Mike Myers book, it also has that the Back-Out Plan DEFINES the steps needed to return to the previous infrastructure.
upvoted 4 times
...
...
Jay5084
3 years, 8 months ago
Read it carefully, which one of the following would provide DETAILS......
upvoted 2 times
Nirue
2 years, 9 months ago
if your saying C is the answer your failing core 2
upvoted 2 times
...
shakevia463
3 years, 8 months ago
Jay did you take this test yet if not update after you do on the results
upvoted 7 times
...
banditring
3 years, 8 months ago
Jay5084, how about you explain an answer instead of saying "Read it carefully". Its bad enough CompTIA has bullshit questions and ridiculous answers to go with it already.
upvoted 11 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago