If you read the copy and paste from exam objectives above in the comment you replied to, you'd see that "validate change" is directly after implementing the change. The answer is clearly B.
A: Verify the change isn't an available selection.
Once an approved change has been implemented, the following steps should be accomplished next:
Verify the change: The project manager should verify that the implemented change has been completed correctly and meets the project's requirements. This may involve testing the change and verifying that it has been integrated into the project as planned.
Document the change: The project manager should document the implemented change, including the details of the change request, the change management process, and any testing or verification that was completed.
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
elvancedonzy
Highly Voted 3 years, 11 months agoSQLDON
3 years, 11 months agoproject_tester
3 years, 7 months agojoe99999
Most Recent 2 years, 1 month agobrvndvnwolf
2 years, 5 months agoExamTopics274
2 years, 5 months ago