exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 429 discussion

Actual exam question from CompTIA's PK0-004
Question #: 429
Topic #: 1
[All PK0-004 Questions]

A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?

  • A. Immediately send the current weekly status report
  • B. Add email to the distribution list for the weekly status report
  • C. Remove email from the distribution list for the monthly status report
  • D. Consult the communications plan and act accordingly
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TreeeSon
2 years, 1 month ago
This question has very bad answers. Not cause the answers are bad in theory but it can be construed in various ways. "A" seems like the best step, then "B" to follow. However, I can see B being valid because chances are you want to prevent this issue in the future. By the PM adding the stakeholder to the distribution list first then he will not have to worry about this being an issue in the future or possibly getting distracted and forgetting to add the stakeholder to the list. You can always add the stakeholder to the list then send the weekly report.
upvoted 1 times
...
MJVIS
2 years, 2 months ago
Based on the situation presented, the best next step for the project manager would be to immediately send the current weekly status report. It is important for the project manager to respond quickly to the stakeholder's concerns and ensure that they receive the necessary information. The project manager should also investigate why the stakeholder did not receive the previous weekly status reports by looking into the communication and taking necessary steps to ensure that it does not happen again in the future. Additionally, the project manager can update the communication plan and add the stakeholder's email address to the distribution list for the weekly status report to prevent any further communication issues.
upvoted 1 times
...
[Removed]
2 years, 9 months ago
check the communication plan. If the stakeholder is down as having only monthly updates, it might need to be updated or verified with the stakeholder.
upvoted 1 times
...
HanzoShimada
3 years, 2 months ago
Personally, I see it as the Project Manager should send it out immediately since it was missed and a concern was raised and THEN add it to the weekly list. I believe A.
upvoted 2 times
...
kadezalei
4 years ago
This should be D.
upvoted 3 times
HelloMyNameIs
3 years, 11 months ago
I'm not entirely convinced the answer is D, I can see the case for it, but it says "consult the communications plan and act accordingly" which seems to suggest the project manager simply looks at the comm plan and does what it says rather than what the stakeholder is actually interested in. Would the PM go back to the stakeholder and say, "Sorry, you're not included in the comm plan, you're out of luck." I could be looking at it incorrectly but thought I'd add food for thought in case some others have better insight.
upvoted 7 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago