Exam PK0-004 topic 1 question 461 discussion

Actual exam question from CompTIA's PK0-004
Question #: 461
Topic #: 1
[All PK0-004 Questions]

A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take
FIRST?

  • A. Submit a change request to the CCB.
  • B. Implement the change to the project.
  • C. Determine the impact of the requested change.
  • D. Update the schedule to accommodate the change.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kadezalei
Highly Voted 4 years ago
This is correct. CompTIA's 5-step Change Management Process: 1 - Identification 2 - Documentation (change request form) 3 - Analysis of impact 4 - Course of action (approve/reject) 5 - Update related plans
upvoted 5 times
elvancedonzy
3 years, 11 months ago
Sounds more like A
upvoted 3 times
...
...
joe99999
Most Recent 2 years, 1 month ago
C When a key stakeholder communicates a significant project scope change to the project manager, the project manager should take the following actions first: -Acknowledge the request: The project manager should acknowledge the scope change request and let the stakeholder know that they have received it. -Evaluate the impact: The project manager should evaluate the impact of the scope change request on the project's overall objectives, timeline, budget, and resources. This includes assessing the risks and identifying any dependencies that may be affected.
upvoted 1 times
...
catastrophie
3 years ago
So to help everyone out I'll add a few notes to the items listed below. Hope this helps! CompTIA's 5-step Change Management Process: 1 - Identification --- Stake holder has communicated the request to the PM. 2 - Documentation --- PM should estimate its impact on project cost, schedule and any other constraints and then document it as well and complete the Change Request Form 3 - Analysis of impact --- CCB uses the documented PM impact estimate provided on the change request documentation. 4 - Course of action (approve/reject) 5 - Update related plans -- Communicate the changes to all involved.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago