exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 152 discussion

Actual exam question from CompTIA's PK0-004
Question #: 152
Topic #: 1
[All PK0-004 Questions]

A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:

  • A. internal project team.
  • B. key stakeholders.
  • C. affected team members.
  • D. full project team.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
harinezumi
Highly Voted 4 years, 3 months ago
can someone explain why not C. affected team members?
upvoted 10 times
Tom_123
4 years ago
The key difference is an “issue” already has occurred and a “risk” is a potential issue that may or may not happen and can impact the project positively or negatively. Therefore no team is affected.
upvoted 1 times
dyers
3 years, 8 months ago
my knee jerk response to the question was: "A risk, minor impact, no change to triple constraint, why do I need to notify anyone, put it in the risk register and carry on" A risk can still impact a specific team or team members, so notify the affected team members to be on the look out for this risk.
upvoted 1 times
...
...
...
Nhancock
Highly Voted 4 years, 2 months ago
If it is minor impact, why would you notify the stakeholders?
upvoted 8 times
...
CyberRooster
Most Recent 2 years, 1 month ago
A. internal project team. Since the risk has a minor impact and there is no change to the triple constraint, it is not necessary to notify all the stakeholders. It is appropriate to inform the internal project team to ensure they are aware of the risk and can take any necessary actions to manage it.
upvoted 1 times
...
kevzzz
2 years, 8 months ago
Everywhere I read about Risk communication or response I see communicate to the stakeholder. There is never a mention in the project team. Maybe because the project team is already a stakeholder since they have a vested interest in the project? The remainder of the stakeholders are not SMEs but do have a vested interest.
upvoted 1 times
...
catastrophie
3 years ago
Selected Answer: B
The answer B as given is correct. Key stakeholder are absolutely the ones you want to notify, they have skin in the game and what may be minor to the PM might not be for a stakeholder. Risk acceptance is different for everyone and everyone perceives risks differently. Team members don't necessarily need to be made aware of every single risk thats identified in the planning or throughout the project. If a risk event happens then they will look as the risk response plan that is in place and proceed as directed. A stakeholder might have a particular level of risk tolerance and maybe that minor risk is the straw that broke the camels back and they withdraw funding.
upvoted 1 times
...
izz123
3 years, 10 months ago
I would check the risk register and it would tell me what to do based on a pre-determined risk response plan. This question is asking me to take a guess. Let me close my eyes and point. Okay it landed on C. That's my guess.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago