During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.
Which of the following should have occurred to prevent this issue?
izz123
Highly Voted 3 years, 10 months agodyers
3 years, 8 months agoharinezumi
Highly Voted 4 years, 3 months agothorstedc
4 years, 1 month agodyers
3 years, 8 months agodyers
3 years, 8 months agoEP5000
Most Recent 2 years, 1 month agolikeahoss
2 years, 10 months agobrown705
2 years, 9 months agospoiledsalsa
2 years, 10 months agoTreymb6
3 years, 1 month agoharinezumi
4 years, 3 months ago